請教QS一個問題
BQ一面有個item A Qty係100M2
TA有份 Omission and Addition Bill有item A
item A omission Qty. 寫(100M2), 而Addition Qty.寫200M2
咁即係咩意思
The quantity of item A is amended to 200m2
唔該晒
你地由100改到200, 係會減100再加200, 唔係直接加100
this would allow the tenderer to consider to re rate this item due to the change in quantities. the increment (or reduction) altered the basis of price in original tender. a common pratice in the industry. good question.
welcome to discuss.