今年咁差係因為無批工程?
渣住top up degree讀緊top up master
考牌就做緊hkis同ricd probationer, 但真係冇咩training唔知點做
想入consultant train但未有offer
有冇師兄可以指點下
揾左成日月都未有offer
依加qs個市真係咁靜?
想做返building team
consultant 應該幾時都等人用架喎
in左觀塘果間a字頭
有同學之前做過話1星期就有offer, 過左成星期都冇聲氣
等多陣啦, 呢間正常都請,問題係你接唔接受到佢人工
fg人工係ok,仲多過R字頭少少
但係對中層好刻薄
以我所知應該對面海高d, 今年轉左?
轉左名之後係多少少
但係計埋福利同ot錢就唔夠對面海多
consultant 應該幾時都等人用架喎
in左觀塘果間a字頭
有同學之前做過話1星期就有offer, 過左成星期都冇聲氣
等多陣啦, 呢間正常都請,問題係你接唔接受到佢人工
fg人工係ok,仲多過R字頭少少
但係對中層好刻薄
以我所知應該對面海高d, 今年轉左?
轉左名之後係多少少
但係計埋福利同ot錢就唔夠對面海多
揾工/轉工時除咗basic salary外,最緊要睇吓有冇其他福利/allowance
尤其係consultant QS, OT係無可避免的
有D QS firm出bill忙起上來,返埋星期六日的話每個月閒閒地都4-5 千OT錢,有D就得幾舊, 有D甚至冇OT錢
仲有D公司一開始會俾高小小人工呃你入去,但之後每年個升幅就好底
騙徒嘅手法層出不窮,轉工前最好問吓間公司口啤,避免中伏
consultant 應該幾時都等人用架喎
in左觀塘果間a字頭
有同學之前做過話1星期就有offer, 過左成星期都冇聲氣
等多陣啦, 呢間正常都請,問題係你接唔接受到佢人工
fg人工係ok,仲多過R字頭少少
但係對中層好刻薄
以我所知應該對面海高d, 今年轉左?
轉左名之後係多少少
但係計埋福利同ot錢就唔夠對面海多
揾工/轉工時除咗basic salary外,最緊要睇吓有冇其他福利/allowance
尤其係consultant QS, OT係無可避免的
有D QS firm出bill忙起上來,返埋星期六日的話每個月閒閒地都4-5 千OT錢,有D就得幾舊, 有D甚至冇OT錢
仲有D公司一開始會俾高小小人工呃你入去,但之後每年個升幅就好底
騙徒嘅手法層出不窮,轉工前最好問吓間公司口啤,避免中伏
想問下做VO 時PC rate 點adjust?
lump sum BQ嘅話
係咪(Actual rate x new quantity) - (PC rate x BQ quantity) ?
consultant 應該幾時都等人用架喎
in左觀塘果間a字頭
有同學之前做過話1星期就有offer, 過左成星期都冇聲氣
等多陣啦, 呢間正常都請,問題係你接唔接受到佢人工
fg人工係ok,仲多過R字頭少少
但係對中層好刻薄
以我所知應該對面海高d, 今年轉左?
轉左名之後係多少少
但係計埋福利同ot錢就唔夠對面海多
揾工/轉工時除咗basic salary外,最緊要睇吓有冇其他福利/allowance
尤其係consultant QS, OT係無可避免的
有D QS firm出bill忙起上來,返埋星期六日的話每個月閒閒地都4-5 千OT錢,有D就得幾舊, 有D甚至冇OT錢
仲有D公司一開始會俾高小小人工呃你入去,但之後每年個升幅就好底
騙徒嘅手法層出不窮,轉工前最好問吓間公司口啤,避免中伏
無ot錢咪撚做啦
不過以我所知都唔係好多間有ot錢
想問下做VO 時PC rate 點adjust?
lump sum BQ嘅話
係咪(Actual rate x new quantity) - (PC rate x BQ quantity) ?
幫推,希望有人解答
想問下做VO 時PC rate 點adjust?
lump sum BQ嘅話
係咪(Actual rate x new quantity) - (PC rate x BQ quantity) ?
幫推,希望有人解答
The PC rate is for supply of material only and usually appears in the item description. The rate for the item includes fixing and installation. Assuming your lump sum contract is with quantities then the adjustment (actual supply rate - PC rate) should apply to the unit rate for the item.
想問下做VO 時PC rate 點adjust?
lump sum BQ嘅話
係咪(Actual rate x new quantity) - (PC rate x BQ quantity) ?
幫推,希望有人解答
The PC rate is for supply of material only and usually appears in the item description. The rate for the item includes fixing and installation. Assuming your lump sum contract is with quantities then the adjustment (actual supply rate - PC rate) should apply to the unit rate for the item.
想問下做VO 時PC rate 點adjust?
lump sum BQ嘅話
係咪(Actual rate x new quantity) - (PC rate x BQ quantity) ?
幫推,希望有人解答
The PC rate is for supply of material only and usually appears in the item description. The rate for the item includes fixing and installation. Assuming your lump sum contract is with quantities then the adjustment (actual supply rate - PC rate) should apply to the unit rate for the item.
者係BQ 個 pc rate item個rate係all-in unit rate黎(pc rate + installation & P&O)
VO個陣就將則師confirmed個actual rate for material + (installation & P&O) x (new quan - BQ quantity) = addition / omission
利申:岩岩grad 尻up未做過 有錯各位屌細力啲:~
想問下做VO 時PC rate 點adjust?
lump sum BQ嘅話
係咪(Actual rate x new quantity) - (PC rate x BQ quantity) ?
幫推,希望有人解答
The PC rate is for supply of material only and usually appears in the item description. The rate for the item includes fixing and installation. Assuming your lump sum contract is with quantities then the adjustment (actual supply rate - PC rate) should apply to the unit rate for the item.
者係BQ 個 pc rate item個rate係all-in unit rate黎(pc rate + installation & P&O)
VO個陣就將則師confirmed個actual rate for material + (installation & P&O) x (new quan - BQ quantity) = addition / omission
利申:岩岩grad 尻up未做過 有錯各位屌細力啲:~
(Adjusted Rate x New Quantity) - (Supply install BQ rate x BQ Quantity)
想問下做VO 時PC rate 點adjust?
lump sum BQ嘅話
係咪(Actual rate x new quantity) - (PC rate x BQ quantity) ?
幫推,希望有人解答
The PC rate is for supply of material only and usually appears in the item description. The rate for the item includes fixing and installation. Assuming your lump sum contract is with quantities then the adjustment (actual supply rate - PC rate) should apply to the unit rate for the item.
者係BQ 個 pc rate item個rate係all-in unit rate黎(pc rate + installation & P&O)
VO個陣就將則師confirmed個actual rate for material + (installation & P&O) x (new quan - BQ quantity) = addition / omission
利申:岩岩grad 尻up未做過 有錯各位屌細力啲:~
(Adjusted Rate x New Quantity) - (Supply install BQ rate x BQ Quantity)
contract寫點adjust咪點adjust 邊個話一定係actual supply rate-pc rate
想問下做VO 時PC rate 點adjust?
lump sum BQ嘅話
係咪(Actual rate x new quantity) - (PC rate x BQ quantity) ?
幫推,希望有人解答
The PC rate is for supply of material only and usually appears in the item description. The rate for the item includes fixing and installation. Assuming your lump sum contract is with quantities then the adjustment (actual supply rate - PC rate) should apply to the unit rate for the item.
者係BQ 個 pc rate item個rate係all-in unit rate黎(pc rate + installation & P&O)
VO個陣就將則師confirmed個actual rate for material + (installation & P&O) x (new quan - BQ quantity) = addition / omission
利申:岩岩grad 尻up未做過 有錯各位屌細力啲:~
(Adjusted Rate x New Quantity) - (Supply install BQ rate x BQ Quantity)
contract寫點adjust咪點adjust 邊個話一定係actual supply rate-pc rate
因為見preamble通常寫話contract rate will be adjusted by the net difference between the prime cost rate and the actual price 所以先咁講。咁我想問下實際上仲有咩可能嘅情況會出現?