我覺得兩方面啦
你好難要求commercial decision 下下就晒 technical, 鬼唔知一早定晒subcon / supplier 好咩,但做唔到嘅時候就要adept
一邊起一邊改design 呢啲嘢香港d濕尻業主一直都係咁做,咁點解CAD 應付到BIM應付唔到? 你睇下班modeller 畫乜7就明
一個二個outsource 去大陸越南菲律濱就肯定係死路一條, 但係就算係香港本地做,甚至係in-house BIM team 都好, 好多時都係白紙無sense 鳩畫嘅。 問題係要訓練到一張白紙有sense,閒閒地都三五年 site exp. (係講緊真係有同engineer/師傅/site works team 夾嘅exp, 唔係坐喺site閉門造車嗰種),香港有咁嘅experience 嘅modeller/coordinator,我懷疑有無一百個
講到尾,本來BIM 就應該同CAD一樣係engineer / builder PC 畫嘅 , 係以前做壞規矩貪平搵班吹水sales佬BIM manager 帶住班乜都唔識嘅modeller 頂住個雞頭先搞到而家啲BIM 整體水平咁弱雞